Assessing Allocation
Factor | Risk Allocation |
No payment at the end of the contract term on the transfer of the asset back to government. | More likely to be government risk |
Payment by government at the end of the contract term. | More likely to be Project Company risk if market based payment More likely to be government risk if pre-determined payment |
Assert reverts to Project Company at the end of the contract term. | More likely to be Project Company risk |
Government sets the contractual hand over conditions at the end of the term. | More likely to be government risk |