18.4.3 Private party's right to proceed
The private party may carry out the Modifications only if its proposal is approved by government. Where it is so approved, the private party must implement the Modification at its own cost, in accordance with its proposal and any conditions of government's approval and otherwise in accordance with all the design, construction, commissioning, operation and maintenance provisions of the project agreement as if it were part of the original works or project activities.