24.1.3  Force Majeure Event

After the occurrence of an Uninsurable Force Majeure Event, or in the circumstances set out in section 20.3.1 of Chapter 20 (Force Majeure), government may terminate the project agreement by notice in accordance with section 20.3 of Chapter 20 (Force Majeure) and will be liable to pay the private party a Termination Payment in accordance with section 25.2 of Chapter 25 (Termination Payments).