9.2.2 Other warranties
The private party will also warrant that:
(a) it has checked and considered the Output Specification;
(b) except for costs resulting from any risks expressly accepted by the government, it has allowed for all risks and costs associated with complying with its obligations to the government under the Project Contracts;
(c) the design of the project works (including all design documentation) will be fit for the intended purposes and will be completed according to, and satisfy the requirements of, the Project Contracts; and
(d) construction of the project works according to the design will satisfy the requirements of the Project Contracts.