10.5.7 Close-Out

After Completion has been achieved, the private party is obliged to expeditiously and diligently progress the balance of the works required to achieve Close-Out. This will occur when the private party has completed:

(a) the balance of the works outstanding as at Completion, including correcting all defects specified in the Certificate of Completion; and

(b) the private party has done everything required to be done by the Project Contracts (including the Output Specification) as a condition precedent to Close-Out.41

A process similar to that which applies to Completion in section 10.5.1(b) will then apply for determining whether Close-Out has occurred.