14.2.2 Timing and Security

Any payment or contribution should be structured to protect the government against construction risk.

Payments made following Completion provide the lowest risk to government. However, government may consider making payments during the construction term where such payments are appropriately secured to protect the government against its increased exposure to construction risk.