14.2.5 Set off
Government may set off amounts payable to the private party under the Project Contracts against any amounts owing by the private party to government or paid by government on the private party's behalf. (This may not include the project debt proportion of any Termination Payment.
The private party must make all payments under the Project Contracts without set off, counter-claim, deduction or withholding.