21.1.1  Repair or Reinstate

If any part of the site, the facility or the works is damaged or destroyed or cannot be used or occupied, the private party must, at its cost:

(a)  promptly repair or replace or remedy the loss or damage so that, to the greatest extent possible, the private party continues to comply with its obligations under the project agreement;

(b)  manage all repair and replacement activities so as to minimise the impact on the facility and works;

(c)  promptly provide government with written notice of any such loss or damage and any required replacement, reinstatement or repair; and

(d)  provide government with a further detailed report of all action being taken or to be taken to effect replacement, reinstatement or remedy of the loss or damage (including an estimate of the time such action will take).