21.2 Uninsurable Force Majeure Events

If the loss or damage occurs as a result of an Uninsurable Force Majeure Event, the private party's obligation to carry out repair and reinstatement is suspended until the parties have agreed an outcome in accordance with Key Risk Event regime,76 the matter is resolved in accordance with the dispute resolution procedure in section 30 or the matter is resolved by a decision of a court which is final and binding on the parties, or the project agreement is terminated as described in section 20.3 (Termination for Uninsurable Force Majeure Event).




_______________________________________________________________________________
76
Discussed in Chapter 15 (Relief for Possible Key Risk Events).