33. Restrictions on private party

Principle

The private party must obtain prior government consent to any:

(a) business conduct other than implementation of the project;

(b) amendment of the project agreement or any other agreements to which government is a party;

(c) amendment of the financing documents and material sub-contracts;

(c) assignment or disposal of its interests in the project agreement or other agreements to which government is a party; or

(d) disposal of any interest in the project land or facility.