C. Design
Activity | Description of risk | Risk borne by Contractor | Risk borne by Authority | Comments/Actions to be taken to minimise risk |
C. Design | Design in construction not complying with planning requirements and/or Building Regulation approvals | • cost of redesign • delay in receiving full unitary charge if failure to meet programme dates • potential cost for the provision of alternative accommodation • potential termination if long stop date extended | • Contractor to ensure design requirements and approvals are fully understood and met • Designs approved in Planning applications | |
Stock condition survey and building surveys inaccurate | • Additional work and cost, under-estimate of investment required and unitary charge too low • delay in receiving full Unitary Charge and additional cost of works to contractor • potential costs for providing alternative accommodation • potential termination if long stop date exceeded | • any additional costs incurred as a result of Authority post survey works not being up to standard | • 100% external and substantial 50% plus representative internal survey of property archetypes • Council and Bidders have agreed survey briefs and understand survey findings • Council and Bidders should note exclusions / limitations of stock condition and building surveys • Warranties from Surveyors to Contractor • Bidders should make their own assessment of the necessity for risk pricing by bidder and sub-contractors • Council should make an assessment of their own necessity for risk pricing / affordability provision, if any | |
Structural and/or latent defects become apparent during refurbishment | • Structural or latent defects to be remedied to the extent output specification to be met at contractors cost • under-estimate of investment required and Unitary Charge too low • delay in receiving full Unitary Charge • potential cost of provision of alternative accommodation • potential termination if long stop date exceeded | • latent defects - anything that is agreed ought not to be covered and revealed by stock survey and not otherwise provided for in the PA e.g. that lies outside the output specification | • Warranties from Surveyors to Council and Contractor • Council and Bidders have agreed survey brief and understand survey findings • Council and Bidders should note any exclusions / limitations of stock condition and building surveys • Bidders should make their own assessment of the necessity for risk pricing by bidder and sub-contractors • Council should make an assessment of their own necessity for risk pricing / affordability provision | |
Discriminatory and specific changes in law | • cost of complying with legislation | • Discriminatory and specific changes in law only apply to services. | ||
General changes of law | • delay in receiving full unitary charge if failure to meet programme dates • increased costs | • increased costs | • Will be agreed cap on capital expenditure by reference to a progressive cost share by the Authority | |
Changes in Authority design requirements post financial close | • failure to meet programme dates without compensation • potential capital contribution and/or increased Unitary Charge if design requirements are more costly | • Will be covered by the Authority Change Protocol and procedures in the Contract | ||
Life expectancy of building elements and components | • costs of future works to prolong life expectancy • reduced unitary charge by virtue of unavailability or performance deductions associated with failure to meet target standards | • Warranty from professional team and Contractor / sub-contractors |