C.  Design

Activity

Description of risk

Risk borne by Contractor

Risk borne by Authority

Comments/Actions to be taken to minimise risk

C. Design

Design in construction not complying with planning requirements and/or Building Regulation approvals

 cost of redesign

 delay in receiving full unitary charge if failure to meet programme dates

 potential cost for the provision of alternative accommodation

 potential termination if long stop date extended

 

 Contractor to ensure design requirements and approvals are fully understood and met

 Designs approved in Planning applications

 

Stock condition survey and building surveys inaccurate

 Additional work and cost, under-estimate of investment required and unitary charge too low

 delay in receiving full Unitary Charge and additional cost of works to contractor

 potential costs for providing alternative accommodation

 potential termination if long stop date exceeded

 any additional costs incurred as a result of Authority post survey works not being up to standard

 100% external and substantial 50% plus representative internal survey of property archetypes

 Council and Bidders have agreed survey briefs and understand survey findings

 Council and Bidders should note exclusions / limitations of stock condition and building surveys

 Warranties from Surveyors to Contractor

 Bidders should make their own assessment of the necessity for risk pricing by bidder and sub-contractors

 Council should make an assessment of their own necessity for risk pricing / affordability provision, if any

 

Structural and/or latent defects become apparent during refurbishment

 Structural or latent defects to be remedied to the extent output specification to be met at contractors cost

 under-estimate of investment required and Unitary Charge too low

 delay in receiving full Unitary Charge

 potential cost of provision of alternative accommodation

 potential termination if long stop date exceeded

 latent defects - anything that is agreed ought not to be covered and revealed by stock survey and not otherwise provided for in the PA e.g. that lies outside the output specification

 Warranties from Surveyors to Council and Contractor

 Council and Bidders have agreed survey brief and understand survey findings

 Council and Bidders should note any exclusions / limitations of stock condition and building surveys

 Bidders should make their own assessment of the necessity for risk pricing by bidder and sub-contractors

 Council should make an assessment of their own necessity for risk pricing / affordability provision

 

Discriminatory and specific changes in law

 cost of complying with legislation

 

 Discriminatory and specific changes in law only apply to services.

 

General changes of law

 delay in receiving full unitary charge if failure to meet programme dates

 increased costs

 increased costs

 Will be agreed cap on capital expenditure by reference to a progressive cost share by the Authority

 

Changes in Authority design requirements post financial close

 

 failure to meet programme dates without compensation

 potential capital contribution and/or increased Unitary Charge if design requirements are more costly

 Will be covered by the Authority Change Protocol and procedures in the Contract

 

Life expectancy of building elements and components

 costs of future works to prolong life expectancy

 reduced unitary charge by virtue of unavailability or performance deductions associated with failure to meet target standards

 

 Warranty from professional team and Contractor / sub-contractors