D.  Ground structure/ environmental contamination

Activity

Description of risk

Risk borne by Contractor

Risk borne by Authority

Comments/Actions to be taken to minimise risk

D. Ground structure/ environmental contamination

Ground structure problems or environmental contamination problems arise which affect building structure, programmed works or availability of accommodation

 cost of additional design works for ground structure problems

 delays in receiving full Unitary Charge

 potential cost of provision of alternative accommodation

 potential termination if long stop date exceeded

 historic site contamination for refurbishment works buildings and their sites

 absence of historic incidences of contamination

 site and ground condition assessments and surveys undertaken by Authority and / or bidders to the extent practical

 works and design provision appropriate to ground structure and environmental contamination risk

 potential for sharing of risk on value for money basis

 insurance against risk