G. Planned Maintenance/ Cyclical Maintenance
Activity | Description of risk | Risk borne by Contractor | Risk borne by Authority | Comments/Actions to be taken to minimise risk |
G. Planned Maintenance/ Cyclical Maintenance | Contractor planned maintenance cost increases | • any costs in excess of budget | • Warranties from Surveyors to Contractor • Bidders have agreed survey briefs and understand survey findings • Bidders should note exclusions / limitations of stock condition and building surveys • Bidders should make their own assessment of the necessity for risk pricing by bidder and sub-contractors | |
Planned maintenance programme delays | • reduced unitary charge associated with failure to meet target standards | |||
Structural and / or altent defects becoming apparent | • Structural or latent defects to be remedied to the extent output specification to be met at contractor's cost • under-estimate of investment required and Unitary Charge too low • reduced unitary charge associated with failure to meet target standards | • latent defects - Anything that is agreed ought not to be covered and revealed by stock survey and not otherwise provided for in the PA e.g. lies outside the output specification | • Risk pricing by Contractor and Sub-Contractor • Defects to be remedied to extent needed to meet output specification |