G.  Planned Maintenance/ Cyclical Maintenance

Activity

Description of risk

Risk borne by Contractor

Risk borne by Authority

Comments/Actions to be taken to minimise risk

G.  Planned Maintenance/ Cyclical Maintenance

Contractor planned maintenance cost increases

 any costs in excess of budget

 

 Warranties from Surveyors to Contractor

 Bidders have agreed survey briefs and understand survey findings

 Bidders should note exclusions / limitations of stock condition and building surveys

 Bidders should make their own assessment of the necessity for risk pricing by bidder and sub-contractors

 

Planned maintenance programme delays

 reduced unitary charge associated with failure to meet target standards

 

 

 

Structural and / or altent defects becoming apparent  

 Structural or latent defects to be remedied to the extent output specification to be met at contractor's cost

 under-estimate of investment required and Unitary Charge too low

 reduced unitary charge associated with failure to meet target standards

 latent defects - Anything that is agreed ought not to be covered and revealed by stock survey and not otherwise provided for in the PA e.g. lies outside the output specification

 Risk pricing by Contractor and Sub-Contractor  

 Defects to be remedied to extent needed to meet output specification