37.9  Rights of Set Off

The Contractor shall not be entitled to retain or set off any amount due to the Authority by it, but the Authority may (subject to clause 55.2 (Set Off on Termination)) retain or set off any amount owed to it by the Contractor under this Agreement which has fallen due and payable against any amount due to the Contractor under this Agreement.