52.2 to 52.6
52.2 If the amounts referred to in clauses 52.1.2 and/or 52.1.3 are less than zero, then, for the purposes of the calculation in clause 52.1 they shall be deemed to be zero.
52.3 If the aggregate of the amounts referred to in clauses 52.1.1, 52.1.2 and 52.1.3 is less than the Revised Senior Debt Termination Amount, then the Force Majeure Termination Sum shall be increased so that it is equal to the aggregate of the Revised Senior Debt Termination Amount and the amount referred to in clause 52.1.4 provided always that:
52.3.1 the amount referred to in clause 52.1.4 shall only be paid to the extent that the Contractor has demonstrated to the reasonable satisfaction of the Authority that the amount will not be paid in payment (in whole or in part) of any Distribution; and
52.3.2 if, at the time of termination, there are any Additional Permitted Borrowings outstanding, no Sub-Contractor Breakage Costs shall be paid in respect of any Sub-Contract in circumstances where there is an event of default under such Sub-Contract which would entitle the Contractor to terminate such Sub-Contract.
52.4 If a Distribution is made whilst any Additional Permitted Borrowing is outstanding and the Contractor has wilfully, or through gross negligence, failed to comply with its obligations under clause [** ] of the Direct Agreement then in addition to the deduction of the Distribution referred to in paragraph (v) of the definition of Revised Senior Debt Termination Amount, the Authority shall be entitled to set off the value of that Distribution a second time against the Force Majeure Termination Sum, provided that the amount of the Force Majeure Termination Sum will never be less than the Revised Senior Debt Termination Amount.
52.5 On termination, the Authority shall have the option to require the Contractor to transfer to the Authority all of its right, tile and interest in and to the Assets.
52.6 If the Contractor has wilfully or through gross negligence failed to comply with its obligations under clause [** ] of the Direct Agreement and there has been an overstatement of the cash balances by the Contractor as at that date which has caused the Authority to reasonably believe that it would be required to pay a lesser sum at the Termination Date than it actually is required to pay under the terms of this clause 52 (Compensation on Termination for Force Majeure), then the Force Majeure Termination Sum shall be reduced by the amount of such overstatement (to the extent such overstatement is still applicable at the Termination Date), provided that the amount of the Force Majeure Termination Sum will never be less than the Revised Senior Debt Termination Amount.