58.1  Occurrence

If and to the extent that a Relief Event:

58.1.1  is the direct cause of either a failure by the Contractor

(a)  to commence the Works on or before the Start on Site Date; and/or

(b)  to achieve Services Availability on or before a relevant Planned Services Availability Date or (following the relevant Planned Services Availability Date but before the Longstop Date) is the direct cause of a delay in achievement of Services Availability; and/or

(c)  [to achieve completion of the Post Completion Works on or before the relevant Planned Post Completion Works Acceptance Date or (following the relevant Planned Post Completion Works Acceptance Date) is the direct cause of a delay in completion of the relevant Post Completion Works]; or

58.1.2  adversely affects the ability of the Contractor to perform any of its obligations under this Agreement,

then the Contractor shall be entitled to apply for relief from any rights of the Authority arising under clause 41.3 (Termination on Contractor Default) [and its obligations under this Agreement].