61.2  Notice to the Contractor

If clause 61.1 (Right to Step-In) applies and the Authority wishes to take action, the Authority shall notify the Contractor in writing of the following:

61.2.1  the action it wishes to take;

61.2.2  the reason for such action;

61.2.3  the date it wishes to commence such action;

61.2.4  the time period which it believes will be necessary for such action; and

61.2.5  to the extent practicable, the effect on the Contractor and its obligation to carry out the Works and/or provide the Services during the period such action is being taken.