2.2
2.2 The time lag for calculating the Unavailability and Service Failure Deductions means no Deductions will be payable in the first Payment Period and Deductions incurred in the first Payment Period will be accounted for in the calculation of the Monthly Service Payment for the second Payment Period and so on throughout the Contract Period.9
___________________________________________________________________________________________________________________________
9 The aspiration in the mechanism however is for Contractors to provide an integrated Helpdesk that can collate the performance and availability information to enable this lag to be removed which 4Ps considers to be best practice.