3 Change Process
3.1 Either party may serve a Change Notice proposing a Change and such Change Notice shall be processed in accordance with the following sections of this Change Protocol:
(a) an Authority Change to the Works, the Services or the Facilities which is a Low Value Change shall be processed in accordance with Part 2 (Low Value Change) of this Change Protocol;
(b) an Authority Change to the Works, the Services or the Facilities which is a Medium Value Change shall be processed in accordance with Part 3 (Medium Value Change) of this Change Protocol;
(c) an Authority Change to the Works, the Services or the Facilities which is a High Value Change shall be processed in accordance with Part 4 (High Value Change) of this Change Protocol; and
(d) a Contractor Change to the Works, the Services or the Facilities shall be processed in accordance with Part 5 (Contractor Change) of this Change Protocol.