12.2 The Core Investment Programme
The parties acknowledge that the Core Investment Programme shall:
(a) set out a planned programme for the provision of the Core Investment Programme Service during the Core Investment Programme Period;
(b) include without limitation the following information:
(i) a detailed plan, on a street by street basis, of the Core Investment Programme Service to be performed in the three (3) Months following the planned date of the commencement of the Core Investment Programme and the date of any updated Core Investment Programme;
(ii) a plan, on a Ward by Ward basis, of the Core Investment Programme Service to be performed in the twelve (12) Months following the date of the commencement of the Core Investment Programme and the date of any updated Core Investment Programme; and
(iii) a schedule in the form of a Gantt Chart of the Core Investment Programme Service to be performed over the remaining period of the Core Investment Programme Period setting out the numbers and types of Apparatus to be removed for each Month during the Core Investment Programme Period;
(iv) having made due enquiry, details of all significant transportation projects or other programmes of works that the Authority (as Highways Authority) or a third party is planning to carry out during the Core Investment Programme Period and details of how the Service Provider has incorporated any changes required by the Authority pursuant to the Review Procedure;
(v) having made due enquiry, details of the relevant activities of any Statutory Undertaker in the affected streets and how the Service Provider intends to co-operate with the same;
(c) comply with the provisions of Method Statement 1A (Core Investment Programme).