12.7  Milestones

The Milestones and the Milestone Completion Dates (Projected) shall be as set out in Table 1 below:

Table 1

1

2

3

Milestone

Milestone Completion Date (Projected)

Percentage of Total

1

6 Months after the Planned Service Commencement Date

[%] of Total to be removed

2

12 Months after the Planned Service Commencement Date

[%] of Total to be removed

3

18 Months after the Planned Service Commencement Date

[%] of Total to be removed

4

24 Months after the Planned Service Commencement Date

[%] of Total to be removed

5

30 Months after the Planned Service Commencement Date

[%] of Total to be removed

6

36 Months after the Planned Service Commencement Date

[%] of Total to be removed

7

42 Months after the Planned Service Commencement Date

[%] of Total to be removed

8

48 Months after the Planned Service Commencement Date

[%] of Total to be removed

9

54 Months after the Planned Service Commencement Date

[%] of Total to be removed

10

60 Months after the Planned Service Commencement Date

[%] of Total to be removed

and Total means the total number of CIP Apparatus.6




________________________________________________________________________________

6  It is important that the Certification process requires all the Illuminated Traffic Signs in an area to be removed/replaced in line with the requirements of the Output Specification prior to the street/area being Certified.  This is the case even if the PS1 Adjustment excludes Illuminated Traffic Signs.  Therefore a separate column may be included for Illuminated Traffic Signs.  CIP Apparatus should be defined as the Existing Apparatus which is to be replaced as part of the CIP Service - usually Lighting Columns or Lighting Points.  On a project specific basis, the Authority may wish to treat Illuminated Traffic Signs separately.