13.14  Failure to Complete Snagging

Where the Service Provider fails to rectify the Snagging Items in accordance with the provisions of clause 13.13, then:

(a)  [paragraph 6.5(g) of the Output Specification and] paragraph 3 of Part 2 of the Payment Mechanism shall apply; and

(b)  the Authority shall be entitled to serve written notice on the Service Provider requiring such works to be carried out within twenty (20) Business Days of receipt of such notice, failing which the Authority shall be entitled to carry out necessary works to rectify the Snagging Matters and the Service Provider shall pay the Authority's costs and expenses reasonably and properly incurred in the carrying out of such works within twenty (20) Business Days of receipt of an invoice from the Authority.  Upon payment of such invoice [paragraph 6.5(g) of the Output Specification and] paragraph 3 of Part 2 of the Payment Mechanism shall cease to apply.