44.5 Termination
If no terms are agreed pursuant to clause 44.4 on or before the date falling one hundred and twenty (120) days after the date of the commencement of the Force Majeure Event and such Force Majeure Event is continuing or its consequence remains such that the Affected Party is unable to comply with its obligations under this Contract for a period of more than one hundred and eighty (180) days, then, subject to clause 44.6, either party may terminate this Contract by serving a written Termination Notice to the other party and this Contract shall terminate twenty (20) Business Days after receipt of such Termination Notice.