Termination of Agreement (Clause 1.10)
2.53 Clause 1.10.1 expresses the intention of the Authority and the Contractor that TUPE should apply to the future provision of all or any of the Services but the exact position will be determined according to the law at the date of termination or expiry of the Agreement.
2.54 Clause 1.10.2 requires that on expiry or termination of the Agreement the Contractor will ensure it has paid all its liabilities in respect of all employees who will return to the Authority. The Contractor is also required to confirm that it and its Sub-Contractors will remain responsible for all their employees (other than those employees returning to the Authority) and would indemnify the Authority or any future contractor or service provider against any direct losses resulting from any claim arising from the employees who remain with the Contractor/Sub-Contractor.
2.55 For employees who return to the Authority, the Contractor is required to indemnify the Authority and any future contractor or service provider against all direct losses incurred by them resulting from a claim by any returning employee concerning anything before the date upon which they return to the Authority or become employed by the future contractor or service provider.