2.1  Schedule of Accommodation

The Schedule of Accommodation is to be developed by the Contractor and agreed by the Authority prior to Financial Close.

The Contractor shall base the provision of accommodation on the detail set out in [The Schedule of Accommodation (Reference)]

For the avoidance of doubt, the areas quoted in the Contracting Authority's indicative schedule are based on clear internal wall to wall dimensions.  The Contractor's Schedule of Accommodation shall be derived and defined on the same basis.