Unavailability Deduction

The sports hall roof at Leisure Facility X has as leak and there is water all over the badminton courts. It is not contained (high priority within 10 mins) but is rectified within an hour.

An Unavailability deduction is to be made as follows;

Unavailability Failure

Priority Level = High

Containment Time = 10 mins

Rectification Time = 1 hour

UD = ( UCn x ZW  x EC  )       x R

            (TOP)

Unitary Charge (UCn)=  (say) £1,000,000

Zone Weighting (ZW) = 20% relating to the Sports Hall

Event Category (EC) = B = 50%

Contract Days (OD) = 362

Unavailability Deduction is £1,000,000  x 20% (zone weighting) x 50% (event category weighting) divided by 724 periods (number of operational periods facility is open) = £138.12 (charge for single operational period).