Bidders should provide a Delivery Programme identifying:

 critical path;

 key client approval/action dates;

 the periods required and key dates for the delivery of the necessary statutory consents and approvals;

 key dates and events in the calendar year, including times when particular pressures are placed on the Services; and

 key access and handover dates and key dependencies upon the Authority and/or other third parties.