2.1 Service Provider's Pre-Completion Commissioning
The Service Provider's Pre-Completion Commissioning will comprise, in relation to the Works, the following activities:
(a) finalisation of the commissioning brief and procedural documentation in accordance with the Authority Construction Requirements;
(b) commissioning and testing necessary to meet the Authority Construction Requirements and the Completion Criteria;
(c) obtaining approvals/licences to meet the relevant statutory requirements and/or required for the operation of the Facilities comprising the Works;
(d) providing reasonable co-operation to the Authority to facilitate the Authority obtaining all licences and approvals;
(e) clinical cleaning including swab tests;
(f) disposal of all equipment packaging arising from the Works;
(g) training of nominated Authority staff, to be within time periods shown in the Outline Commissioning Plan to suit the Commissioning Programme;
(h) notice of the required date of delivery of Authority Equipment which notice shall be in sufficient time to allow the Authority to procure such equipment.