3.1 The Service Provider's Post-Completion Commissioning
The Service Provider's Post-Completion Commissioning will be carried out after the Actual Completion Date in accordance with the Final Commissioning Plan and will comprise:
(a) testing and balancing the re-calibration, comprising adjustment and final connection, of services and associated environmental systems where:
(i) post-completion installation of transferred items of Authority Equipment entails connection to previously installed services; and/or
(ii) post-completion installation of transferred items of Authority Equipment imposes a load on or adjustment to previously installed services; and/or final occupancy levels impose a load on the installed services and environmental systems;
(b) rectification of all Snagging Matters in accordance with clause 21.11 (Carrying Out of Snagging);
(c) clinical cleaning including swab tests;
(d) autoclave tests and accreditation by a suitably qualified person;
(e) completion of post-completion outstanding matters as agreed with the Authority;
(f) rectification where there is damage to the fabric of any of the Works that is attributable to any act or default of the Service Provider in undertaking its post-completion commissioning activities or in carrying out the Works.