Component of the Works | Criteria | Tests |
Building Structure | Foundations have been constructed on appropriate bearing strata constructed to current Codes of Practice taking into account the loadings to be sustained, prevailing ground conditions and the effects of any settlement on new superstructure and on links to adjacent buildings. Structures supporting sensitive equipment to be robust with deflection and vibration characteristics which are in compliance with the Project Documents. | Compliance with British Standards, Code of Practice and Building Regulation Certificate of Compliance. Details of imported fill compliance with Highways Agency "Specification for Highways Works". Results of static load tests on piles carried out in accordance with Institution of Civil Engineers" Specification for Piling Works " Results of integrity tests on piles carried out in accordance with Institution of Civil Engineers "Specification of Piling Works" Details and results of any contamination testing to be carried out by UKAS accredited laboratory.Inspection reports on water excluding structures (basements) with reference to BS[♦]. Summary report of concrete cube tests results carried out to British Standards. Summary report of mortar compression test results carried out to British Standards. Intumescent coating manufacturer's inspection reports and intumescent fire resistance certificates. |
Roads and Paving | To comply with the requirement of the Highway Agency Manual of Contract Documents. As described in the Authority Construction Requirements. | Material conformance certificates and compliance with Project Documents. |
Below Ground Drainage | Drains to be free from obstruction to achieve design flow rates and do not leak. | Components are to comply with British Standards [list relevant standards]. Results of water tests to drains carried out to BS[♦] and "Sewers for Adoption". Results of water tests to manholes carried out to BS[♦]. Material conformance certificates and compliance with the Project Documents. |
External Walls | Compliance with the Project Documents. Internal noise level requirements to comply with HTM 2045, and HTM 2025.
No water penetration or interstitial condensation evident. | To be supported with evidence of calculations demonstrating compliance with performance requirements including, permeability, water tightness, resistance to wind loads and fire performance, to British Standards (list relevant standards) and Codes of Practice. Acoustic Tests to BS[♦] (measurement of sound insulation in buildings and of building elements). Visual inspection. In accordance with BS(♦). Local Authority sign off Confirmation that Parts L1, L2 of Building Regulations are met. Receipt of manufacturers test results where applicable. |
Internal Walls and Partitions | All partitions shall have the ability to resist the passage of fire and maintain integrity and stability. Partitions shall be set accurately to line, level and plumb, and within permissible deviations. No constituent material shall promote or sustain the growth of fungi, micro-organisms or insects. Internal noise level requirements to comply with the Project Documents. | Test in accordance with British Standard and test assembly, to height, configuration and plan dimensions as set out on the agreed Fire Strategy drawing and as described in HTM 56 CP 122 and British Standards [list relevant standards]. Visual Inspection. Visual Inspection. Local Authority sign off and written confirmation of rectification of non-conformances for standard rooms Documented results of Acoustic room tests for requirements. Acoustic test to BS[♦] Measurements of sounds insulation in buildings and of building elements to British Standards. |
Windows and External Glazing | Sound; secure and weatherproof; no leakages, easily operated; ironmongery in operating order. Fire resistance of all external glazing shall be in accordance with the requirements of the British Standards. Opening lights shall be fitted with restrictors to limit opening to 100mm. Clear air gap. The external glazing must accommodate a design wind pressure calculated in accordance with BS(♦): appropriate to the locality of the facilities, and for the relevant exposure and height of building. | Test in accordance with British Standards (list relevant standards).
|
Roofs | Sound transmittance of roof shall conform with the internal noise level requirements of HTM 2045 and as described in the Project Documents. Calculate wind loads on roof in accordance with British Standards. Water penetration must not occur under site exposure conditions.
Roofs and roof voids to which access is provided to have protection to satisfy Building Regulations and Health and Safety Regulations. | Test in accordance with British Standards (list relevant standards) and the Project Documents
Tested in accordance with British Standards [list relevant standards] for water absorption and wetting and drying. Also visual inspection. Test in accordance with British Standards [list relevant standards)]
Also visual inspection. In accordance with BS[♦] Test Method. In accordance with British Standards [list relevant standards]. |
Ceilings | Suspended ceiling must safely support all loads in accordance with the Project Documents. Protective finish and performance requirement shall be in accordance with British Standards and HTMs. All substantial conductive parts of the suspended ceiling are to be electrically continuous and fully earthed bonded in accordance with BS[♦]. Fire spread rating for materials exposed both to the room and the void shall meet the requirements of the British Standards and the Building Regulations. Sound absorption shall be in accordance with HTM 2045. | In accordance with British Standards [list relevant standards]. In accordance with British Standards (list relevant standards). In accordance with British Standards [list relevant standards]. In accordance with British Standards . [list relevant standards]. In accordance with HTMs [list relevant HTMs] and British Standards [list relevant standards]. |
Doors and Ironmongery | All door sets shall comply with the performance requirements in HTM 58. All ironmongery must be covered by a test certificate, including door closers, floor springs and electro-magnetic closer mechanism. Each fire door/ door set shall comply with requirements for fire resistance. | Manufacturer's Certificate. |
Stairs, Walkways and Balustrades. | Stairs, balustradings and handrail loadings shall be as specified in BS[♦]. Detailed dimensions of width and depth for passing and turning when evacuating in an emergency shall be in accordance with HTM 81. Fire resistance of all staircases and enclosures shall comply with the requirements of the Building Regulations and relevant HTMs. | To comply with the requirement of
In accordance with British Standards (list relevant standards). |
Floor and Wall Finishes | Coverings sound; secure and of even surface Floor finishes, screeds and adhesives to comply with Building Regulations, British Standards, British Standards Code of Practices and HTM 61. Extra slip resistance for floor finish to rooms and areas defined on Zone Data Sheets. Particular requirements are to be followed for kitchens. | Visual inspection in accordance with British Standards [list relevant standards]. Inspection in accordance with British Standards [list relevant standards] and Approved RDD Items and room finishes specification set out in [♦]. Evidence of consultation and approval of Environmental Health Officers and to British Standards. |
Signage and Way Finding | All signage for the satisfactory operation of the hospital. | Visual inspection for compliance with Reviewable Design Data signage and wayfinding strategy. |
Fixtures and Fittings | No materials used shall support the growth of bacteria, fungi, etc or encourage the harbouring of insects. | In accordance with British Standards (list relevant standards), Codes of Practice, Evidence of Consultation and approval of Authority's Infection Control Officer. |
Sanitary Appliances and Fittings Accessories | All components shall comply with HTM 64 and the requirements of relevant British Standards (list relevant standards) as listed in the output specifications. Installed in accordance with manufacturer's recommendations. | In accordance with British Standards [list relevant standards].
Visual Inspection. |
Purpose Made Joinery | After machining and fabrication, sections shall be free from twist and bowing, surfaces to be smooth and free from testing, wooliness, chip bruising and other machining defects. | In accordance with British Standards (list relevant standards). Visual Inspection for compliance with 1:20 Reviewable Design Data drawings |
Purpose Made Metalwork | Metal arc welding, TIG welding and MIG welding to BS[♦]. Anodising | In accordance with BS[♦].
|
Carpentry/Timber Framing/ First Fixing | Design and detail the work to BS[♦] to satisfy loading requirements. | In accordance with BS[♦] |
Preservative/Fire Retardant Treatment | Moisture content of timber at time of treatment to be no more than 28% Leach resistant Fire Retardant Treatment: Moisture content at time of treatment 22% for timbers up to 50mm thick. | In accordance with British Standards [list relevant standards]. |
Landscaping | All soft landscaping to meet the requirements of the services performance specifications, workmanship and materials to conform to British Standards. Imported topsoil shall be in accordance with BS[♦] either Premium or Amenity grade general texture. | Visual Inspection in accordance with British Standards [list relevant standards] and landscaping layouts Approved RDD Items. |
Engineering Services | Engineering services as commissioned to be in accordance with the Authority Construction Requirements; CISBE Commissioning Guides (CISBE-CG);NHS Model Engineering Specification; IHEEM- Commissioning of Engineering Services. | Testing of the Works to be carried out to determine compliance with the Project Documents. |
Mechanical Engineerring Systems | Records of percentage testing carried out in the construction and pre-commissioning periods shall be available to demonstrate fitness of systems prior to commencement of commissioning. | Examination and testing to confirm that each system, components and equipment are complete and in a safe condition. |
Heat Source and Distribution - Boilers (Steam) Boilers (LPHW) Steam and Condensate | Setting to work, balancing and regulation to meet design performance. Boiler Plant Output and Efficiencies. Fuel storage and supply systems flow rates. Steams distribution and condensate collection. Pressures and flow rates. Exhaust gas systems instrumentation and controls. Operation of pressure relief and other safety systems. | Engineering services as commissioned to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents, CISBE Commissioning Guides (CISBE-CG). |
Water Systems: Chilled water systems Hydrant System | Setting to work, balancing and regulations to meet design performance: • flow rates; • distribution systems; • outlets; • components; • temperatures; and • safe water temperatures. | Engineering services as commissioned to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents and HTM 2027. |
Ventilation Systems: Mechanical supply Mechanical Clean Extract Specialist Ventilation Services Mechanical Dirty Extract | Setting to work, balancing and regulation to meet design performance and room pressure differentials: • Flow rates; • Distribution systems; • Outlets; • Components Temperatures; and • Instrumentation and controls. | Engineering services as commissioned to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents, - CIBSE Code A - Air distribution systems and HTM 2025 |
Refrigeration: Sealed Units Storage Cabinets Body Stores Deep Freeze Units Cook-Freeze cabinets Chilled water plants Cold rooms | Setting to work, balancing and regulation to meeting design performance: • flow rates; • distribution systems; • outlets; • components; • temperatures; • instrumentation and controls; and • safety and alarm systems. | Engineering services as commissioned to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents, - CIBSE Code R - Refrigerating Systems. |
Fire Protection Installations | Setting to work, balancing and regulation to meet design performance: • fire hydrants; • sprinklers; and • dry riser. | Fire protection Installations to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents, Fire Extinguishing Installations. Fire Code. Sprinklers - test and certify in accordance with Loss Prevention Council Dry Risers - flow and pressure tests. |
Radiological Protection | All components of the works – including external and internal walling, doors, ceilings floors – to meet radiological protection standards where applicable. | Rooms to be tested in accordance with the Authority's Radiological Protection Advisors requirements. |
Electrical Services | Records of tests carried out in the construction and pre-commissioning periods shall be available to demonstrate fitness of systems prior to commencement of commissioning. These shall include but not limited to: • examination and testing to confirm that each system, components and equipment are complete and in a safe condition; • electrical continuity and impendence testing in accordance with 16th Edition of the Wiring Regulations; and • Function tests. | Electrical services to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents.
|
General Electrical Services | Setting to work and functional testing to meet design performance. | Engineering services as commissioned to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents. Common services - electrical (low and extra low voltage). Continuity of ring final circuit conductors. Resistance of protective conductor. Continuity of bonding conductor. Earth loop impendence. Earth electrode resistance. Cable and Switchgear insulation tests. Operation of RCD and fault operated protective devices. Prospective short circuit current and phase impendence. Electrical Installation tests certificate - final circuits to the 16th Edition of the Wiring Regulations. HTM 2020. Electrical Safety Code for low voltage systems. |
HV Services | Setting to work and functional testing to meet design performance. | Engineering services as commissioned to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents and HTM 2021 Electrical Safety Code for high voltage systems. |
Standby Electric Generating Plant and UPS | Standby electric generators shall provide back up in the event of failure of the incoming supply or component failure. Battery backed UPS systems shall supply critical areas such as theatres, in ITU, CCU, PICU, Burns Unit, laboratory areas and other critical computer controlled equipment to meet functional requirements. | Engineering services as commissioned to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents and HTM 2011 Emergency electrical service. Emergency electrical services. |
Lighting Installation | Setting to work to meet design performance. | Engineering services to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents and in accordance with procedures outlined in the CIBSE Lighting Guide - Hospitals and Healthcare Premises and Derogations. |
Emergency Lighting | Setting to work to meet design performance. | Test in accordance with BS[♦]. |
External Lighting Installation | Setting to work and functional testing to meet design performance. | Compliance with Highways Specification. |
Patient/Nurse Call Systems | Operational broadcast points and all speakers operative; points should sound secure; no exposed conductors. | Functional tests and HTM [list relevant HTMs]. |
Bedhead Services | Setting to work to meet design performance. | Functional testing HTM 2015 bedhead services. |
Communal Radio and Television Networks | Setting to work to meet design performance. | Functional testing. |
Fire Detection and Alarm Systems | Setting to work to meet design performance. | Functional testing to demonstrate compliance with BS[♦]. |
Access Control Systems | Setting to work to meet design performance. | Functional testing for security of access and control. |
Security Intruder Alarms / Personnel Attack Alarms | Setting to work to meet design performance. | Functional testing for Internal Security. |
Closed Circuit Television (CCTV) | Setting to work to meet design performance. | Functional testing for Closed Circuit Television. |
Lightning Protection Installations | Setting to work to meet design performance. | Functional testing for Lightning Protections and British Standards. |
Lifts | Setting to work to meet design performance. | Safety and functional testing to BS[♦] and HTM 2024. |
Pneumatic Tube Conveyor | Setting to work to meet design performance. | HTM 2009: Functional testing as required for compliance with Pneumatic air tube transport systems. |
Medical Gases: Oxygen Nitrous Oxide Surgical Compressed Air Medical Compressed Air Medical Vacuum Medical Gas Alarm System Anaesthetic Gas Scavenging Laboratory Gases Liquid Nitrogen | Medical and Laboratory gases available, vacuum / suction available, anaesthetic gas scavenge systems shall be available at the specified flow rate and pressure defined in the Authority's Construction Requirement at all outlets within the room. Medial Gas Pipelines: • flow rate; • pressure; • vacuum; • anti-confusion; and • cleanliness | Engineering services as commissioned to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents including HTM 2022. Medical Gas, pipelines and systems to be tested in accordance with HM 2022. Purity - BCGA Code of Practise. |
Public Health | Setting to work to meet design performance. | Functional testing to demonstrate compliance with Above Ground Sanitation Systems BS 5572. Below Ground drainage BS 8301 • water / air testing; • pipelines; • manholes; and • CCTV inspection. |
Building Management Systems | Setting to work to meet design performance. | Functional testing to demonstrate compliance with Building Management systems - HTM 2005 |
Renal Dialysis Water Supply | Setting to work to meet design performance. | Specialist manufacturer to carryout function, sterilisation and purity tests. |
Structured Cabling: Outlets Outlet Cabling Patch Panels / Cabinets Fibre Backbone (internal) Fibre Backbone (external) Copper Backbone (internal) Copper Backbone (external) Patch cords only As fitted drawings Hub Rooms | Full manufactures warranty for cable installation. Certification and test records for the work carried out. | Structured Cabling to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents. Full manufacturer's warranty for cable installation. |
Data Network: LAN Active Equipment Standards of LAN | Compliance with HSE and NHS guidance for IMT&T Setting to work, safety and functional testing to meet design performance. | Tests in accordance with Authority Construction Requirements and to TIA/EEE standards. |
Data Link to existing system | ||
Telephone Systems: PABX Central equipment All system extensions for general telephone use. System extensions for facsimile and modems Switchboard consoles Cordless telephony (incl. Base stations) Paging system and all pagers Call information Logging Equipment PC's for operator consoles only Telephony link to existing systems | Setting to work, safety and functional testing to meet design performance. | Telephone systems to be tested in accordance with the Authority Construction Requirements, for compliance with the Project Documents and supported by a full manufactures warranty for equipment installation. |
Noise and Sound Insulation | To be commissioned in accordance with Town Planning requirements, the Building Regulations and the Authority Construction Requirements including: • site areas testing; • boundary noise level; • internal room level certification; • performance of partitions etc in respect of privacy standards; • plant room breakout to adjoining spaces; and • noise measurement of all plant areas. | Completion of acoustics test in accordance with HTM 2045 and 2025. |
Content, Layout, Size and Shape of Rooms | Compliance with contents listed on Zone Data Sheets including: • Group 1 Equipment and Group 2 Equipment; • clinical services and call systems; • power, LAN, radio, TV, video, telecommunications and transit systems; and • satisfaction of the standards and performance of design parameters. Compliance with 1:50 loaded drawings. | Inspect (%3) rooms to ensure all works are complete and provide the requirements set out in the Zone Data Sheets and 1:50 loaded drawings. |
All Equipment to be supplied and installed in accordance with manufacturer's instructions. | Evidence of test to be in accordance with BS (list relevant standards) and ISO 9000 and manufacturer's recommendations. | |
Planning Permission | Discharge of Conditions | Written evidence of satisfactory discharge of conditions to be provided evidence of submissions made to the Local Authority for approval of any matters outstanding at Practical Completion. |
Highways Works | Section 278, Section 38 works etc | Written evidence of satisfactory completion of any works undertaken in connection with Highways. |
Drainage works | Section 104 etc | Written evidence of the satisfactory evidence of completion of drainage to public sewers. |
Designers Certificate of Compliance | As Part 3 of Schedule 5 (Certificates) of the Project Agreement | Signed certificate to be provided. |
Health and Safety File | To be completed for the Works. | Written statement provided by the Planning Supervisor of the satisfactory provision of information within the Health & Safety File to allow the use and operation of the facility. |
Snagging | The Service Provider's detailed snagging list to be provided. Programme for rectification of snagging to be available. | Sample review of the snagging list in conjunction with final room inspections |
Design Derogations | Schedule of non-conformance to the Project Documents (e.g. departure from HTM and HBN guidance). | Schedule to be provided identifying derogations and dates agreed with Authority Representative |
Maintenance Strategy | Statement for the provision of Hard (and Soft FM) service delivery within the new facilities | Agreed statement provided by the Service Provider to demonstrate FM provider is able to operate the facilities and schedule of any remedial matters to be addressed post Practical Completion |
Practical Completion Outstanding Matters | All issues included on Completion Certificates, including balancing and testing of services, snagging matters completion and outstanding works completion. | Evidence to be provided that all matters complete. (%) sample inspection to be undertaken to verify. |
_______________________________________________________________________________
3 Authority to consider % room sampling and ensure % stated here reflects amount stated in Schedule 15.