2.1  Construction Contractor's Warranties and Undertakings

The Construction Contractor warrants and undertakes to the Authority that it has complied with and fulfilled and shall continue to comply with and fulfil its duties and obligations arising under or by virtue of the Construction Contract, provided that the Authority shall only be entitled to make a claim against the Construction Contractor under this clause 2.1 if the Project Agreement has terminated and shall not be entitled to do so during the Step-in Period or after the Construction Contract has been novated under clause 4 (Novation).