4 Procedure Review
The Independent Certifier shall:
4.1 Monitor the operation of the quality assurance procedures of the Construction Contractor at regular intervals (maximum [three (3)] months) during the execution of the Works.
4.2 The Independent Certifier shall familiarise itself with the proposed procedures and programmes for the testing and commissioning of the [mechanical and electrical engineering services] prior to the Authority's occupation.
4.3 Monitor the procedures for the identification, approval and recording of agreed Changes to the Works in accordance with the Project Agreement.
4.4 Review any samples or mock ups as required by [the Authority Construction Requirements] and check that they have been approved in accordance with the Project Agreement.