14.1 Service Provider Obligations
The Service Provider shall, at its own expense:
(a) subject to clause 14.1(e) obtain all Consents required for the performance of the Project Operations;
(b) implement each Consent within the period of its validity in accordance with its terms;
(c) supply to the Authority Representative a copy of any application for a Consent (with a copy of all accompanying drawings and other documents) and a copy of any Consent obtained;
(d) procure that no Consent is breached by it or any Service Provider Party and use all reasonable endeavours to procure that no Consent is revoked; and
(e) use all reasonable endeavours to assist the Authority to obtain the Authority Consents necessary for the carrying out of the Works.6
_____________________________________________________________________________________________
6 Only applicable in exceptional cases, as the Service Provider should be responsible for obtaining detailed planning permission and all Consents.