18.1 Dates for Completion
The Service Provider shall complete the Works by the Planned Completion Date. Without prejudice to the clauses set out in Part K (Termination and Expiry) and Schedule 22 (Compensation on Termination), the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Planned Completion Date and the Actual Completion Date.