25.2  Change of timing by Authority

Notwithstanding that there has been no objection to a Schedule of Programmed Maintenance pursuant to the Review Procedure:

(a)  the Authority Representative may, at any time, require the Service Provider to accelerate or defer any Programmed Maintenance by giving written notice to the Service Provider, not less than twenty (20) Business Days prior to the scheduled date for carrying out such Programmed Maintenance, which notice shall set out the time and/or periods at or during which the Authority requires the Programmed Maintenance to be performed;

(b)  the Service Provider shall notify the Authority of the amount of any additional reasonable costs which it will incur as a direct consequence of such acceleration or deferment (Estimated Increased Maintenance Costs);

(c)  the Authority shall, within a further period of ten (10) Business Days following receipt by the Authority of notification of the amount of the Estimated Increased Maintenance Costs, at the Authority's option, either confirm or withdraw its request to accelerate or defer the Schedule of Programmed Maintenance;

(d)  if the Authority does not respond within this ten (10) Business Day period, the request shall be deemed to have been confirmed; and

(e)  the Authority shall reimburse the Service Provider the direct and reasonable costs actually incurred by the Service Provider as a consequence of such acceleration or deferment up to, but not exceeding, the amount of the Estimated Increased Maintenance Costs.