6.4 Authority Warranted Data
The Authority warrants to the Contractor that the information set out or described in Part 1 of Schedule 11 (Warranted Data) has been prepared after due and careful enquiry and is reasonably believed to be true, accurate and complete as at the date of this Agreement provided that no inaccuracies or omissions in such information shall be capable of giving rise to an Authority Default.89
_________________________________________________________________________________________
89 This clause should not be used if the only data in Schedule 11 (Warranted Data) is employee information. No warranty is to be given in respect of employee information because the cost adjustment mechanism is being used.