16.5 Effect of a Compensation Event
(a) If, for [any/the] Facility on or before the Services Availability Date [for that Facility], as a direct result of the occurrence of a Compensation Event the Contractor will be unable to either:
(i) commence the Works on or before the Start on Site Date and/or;
(ii) achieve Services Availability on or before the Planned Services Availability Date or (following the Planned Services Availability Date but before the Longstop Date) will be delayed in achieving Services Availability; and/or
(iii) comply with its obligations under this Agreement; and/or the Contractor will incur costs or lose Revenue,
then the Contractor is entitled to apply for an extension of time to the Start on Site Date and/or to the Planned Services Availability Date and/or (following the Planned Services Availability Date) to the Longstop Date and/or relief from its obligations and/or to claim compensation under this Agreement.
(b) [If, for [any/the] Facility where completion of the Works at [that/the Facility] is scheduled to occur after the Planned Services Availability Date, as a direct result of the occurrence of a Compensation Event the Contractor will be delayed in completing such Works on or before the relevant Planned Post Completion Works Acceptance Date or (following such Planned Post Completion Works Acceptance Date, but before the Longstop Date) will be delayed in completing such Post Completion Works or will be unable to comply with its obligations under this Agreement and/or the Contractor will incur costs or lose Revenue in respect of such Works then the Contractor is entitled to apply for an extension of time to the Planned Post Completion Works Acceptance Date and/or relief from its obligations and/or to claim compensation under this Agreement.]