16.9 Failure to Agree
If the parties cannot agree the extent of any compensation, delay incurred, relief from the Contractor's obligations under this Agreement, or the Authority disagrees that a Compensation Event has occurred (or as to its consequences), or that the Contractor is entitled to relief under this clause 16 (Extensions of Time), the parties shall resolve the matter in accordance with the Dispute Resolution Procedure.