46.7  Failure to Carry Out Work

If and to the extent that the Contractor fails to carry out the Outstanding Work within the period specified in clause 46.3.2 (Results of Survey), the Authority shall be entitled to carry out itself, or procure, such rectification and/or maintenance work at the Contractor's expense and shall make withdrawals from the Retention Fund Account or, where there is insufficient funds in the Retention Fund Account, make subject to clause 36.9 (Rights of Set Off) deductions from any subsequent payment of Unitary Charge to pay for such rectification and/or maintenance work or recover such amounts from the Contractor as a debt payable on demand.