54.3  Exclusivity of Remedy

Any payment of compensation pursuant to this Part 7 (Compensation on Termination) shall be in full satisfaction of any claim which can be made against the Authority by the Contractor in relation to termination of this Agreement or any Project Document.  The compensation payable under clauses 51 (Compensation on Termination for Force Majeure), 50 (Compensation on Termination for Contractor Default), 48 (Compensation on Termination for Authority Default/Voluntary Termination/Authority Break Point Date) and 49 (Compensation on Corrupt Gifts, Fraud and Refinancing Breaches) shall be the sole remedy of the Contractor against the Authority in respect of termination of this Agreement.