69.2 Restriction on the Contractor
Subject to clause 69.3 (Exception) and subject always to the provisions of the Direct Agreement, the Contractor shall not sub-contract, assign, underlet, charge, sell, bargain or otherwise deal in any way with the benefit of this Agreement in whole or in part except with the prior written consent of the Authority.210
_________________________________________________________________________________________
210 There may be critical services that are provided by second tier sub-contractors. In these circumstances, the Authority may decide that clauses 69.2 and 69.3 should also apply to such critical services and amendment made to require Authority consent to such providers.