(4.1) PFI contract.
A project contract must be based on accepted standardised contract documentation. With the exception only of LIFT projects, this will be Standardisation of PFI Contracts (SoPC), as well as recognised sector specific guidance, including Building Schools for the Future contracts and 4ps procurement packs. The version used, any addenda, and possible agreement to any derogations, should comply with the most recent instructions issued by HM Treasury.