(6.7)  Timetable.

A timetable should be prepared covering all stages from submission of the initial proposal to start of service provision, bearing in mind that the process has changed recently under the competitive dialogue procedure. In particular a realistic deadline should be proposed to reach contract financial close, with stages of the procurement process kept to a minimum consistent with achieving value for money. This should be consistent with the model procurement timetables in 4ps procurement packs. Authorities are advised to ensure that the timetable and affordability assumptions are consistent.