Table 1A
Ref | |
1 | Compliance with latest Building Regulations and legislative requirements [in all areas where works have been completed]. |
2 | The standards of workmanship and materials used are in accordance with section 5 of this Output Specification. |
3 | The quality standards set out in the Contractors Proposals in Schedule [ ] of the Project Agreement have been attained. |
4 | Compliance with the Full Availability Standards in section 7 of this Output Specification. |
5 | The requirements contained within section 4.6 of this Output Specification have been attained. |
6 | No reduction in floor space from that prior to refurbishment |
7 | Number of windows/size of windows not reduced from that prior to refurbishment |
8 | Works undertaken do not reduce the acoustic performance of the Dwelling from that prior to refurbishment |
9 | All suspected asbestos has been tested and where positive, either: • removed and disposed of properly; or • appropriate management plans have been developed and approved by the Authority. |
10 | All internal and external finishes made good following works |