Table 1D

Ref

Certification Requirement

 

1

Compliance with latest Building Regulations and legislative requirements, including those pertaining to disabled access..

 

2

Compliance with all planning obligations

 

3

Compliance with Full Availability Standards for the Community Centre as set out in section 7 of this Output Specification.

 

4

The standards of workmanship and materials used are in accordance with section 5 of this Output Specification.

 

5

The works are in accordance with the following plans:

 [TBC] 73

 

6

The quality standards set out in the Contractors Proposals in Schedule [ ] of the Project Agreement have been attained.

 




____________________________________________________________________________________________

73 This will contain references to the Contractors agreed community facility drawings.