(06/04/10)
CLG's indicative timescale for procurement of HRA PFI projects is between 30 and 36 months (130 to 156 weeks).
For Non-HRA PFI projects - between 24 to 30 months (104 to 130 weeks).
With reference to the indicative HRA procurement timetable below, this reflects a 156 week / 36 months timetable and provides a "benchmark" for authorities to assist them not to exceed this upper timescale and assist them to plan and manage procurement within the overall 30 to 36 months timescale span that is considered achievable.
Authorities are asked to be realistic in their timescales and to always provide for 6 months sensitivity (Authority funded) on top of a realistic procurement timescale
Procurement Stages and Milestones | Stage Weeks | Cumulative Weeks |
PRG endorsement of OBC | 0 | |
OJEU & Pre Qualification Questionnaire (PQQ) Stage | (12) | 0 |
Finalise and agree Evaluation Framework | 2 | |
Issue OJEU Notice | 1 | |
Issue Scheme Prospectus (Descriptive Document) & PQQ | 1 | |
"Bidders Conference" | 1 | |
Receipt of PQQ submissions | 3 | |
Evaluation of PQQ submissions | 2 | |
Selection of Longlist | Event | |
Authority approval of Bidder Longlist | 2 | |
Feedback to unsuccessful and successful applicants | Process | |
Invitation to Participate in Competitive Dialogue Stage | (9) | 12 |
Invitation to Participate in Competitive Dialogue | 1 | |
Bidder briefings and discussions focusing on ISOS | Process | |
Development and agreement on Survey Proposals, Specifications and Commissioning of Surveys | Process | |
Commencement of Authority / Bidder agreed Surveys to inform both Authority Affordability and Bids at ISDS and IFRS stages | 8 | |
Invitation to Submit Outline Proposals (ISOS) Stage | (13) | 21 |
Issue of ISOS | 2 | |
ISOS dialogue and clarification | Process | |
Receipt of ISOS submissions | 4 | |
Evaluation of ISOS bid submissions | 4 | |
Selection of Shortlist | Event | |
Authority approval of Bidder Shortlist | 3 | |
Feedback to unsuccessful and successful applicants | Process | |
Bidder briefings and discussions focusing on Tender documentation and proposed ISDS process and requirements | Process | |
Pre-ISDS Tender Information and Documentation Preparation | 8 for below | 34 |
Refinement of scheme and proposals taking into account ISOS submissions and bidder views | Process | |
Submission and resolution of council derogations | Process | |
Production, review and acceptance of Survey Reports and Information | Process | |
Finalisation of all Tender documentation | Process | |
Data Room / Website opened and Data CD Roms issued | Event | |
(29) | 42 | |
Issue of ISDS | 8 | |
ISDS dialogue, clarification and negotiations | Process | |
Receipt of ISDS submissions | 12 | |
Evaluation including clarification of ISDS submissions | 6 | |
Selection of Bidders for ISRS (as appropriate / necessary) | 3 | |
Feedback to unsuccessful and successful applicants | Process | |
Invitation to Submit Refined Solutions Stage (ISRS) Stage: a Second Phase of ISDS Stage, as appropriate/ necessary, not obligatory | (18) | 71 |
Bidder briefings and discussions focusing on Tender documentation and proposed ISRF process and requirements | Process | |
Issue of ISRS | 4 | |
ISRS dialogue, clarification and negotiations | Process | |
Receipt of ISRS submissions | 8 | |
Bid evaluation including clarification of ISRS bid submissions | 4 | |
Feedback to Bidders | 2 | |
Pre-Close of Dialogue (inc. Phase 1 of PRG 2nd Stage Review if selected) | 8 for below | 89 |
Submission, review and approval of all potential derogations | Process | |
Phase 1 of PRG 2nd Stage Review (if selected) with the aim of accommodating within the overall 8 wks | (3) | |
Assess readiness to Close Dialogue | Process | |
Close Dialogue & Call for Final Tenders | Event | |
Final Tenders (FT) Stage | (7) | 97 |
Receipt of Final Tenders | 3 | |
Bid Evaluation including clarification of FT submissions | 4 | |
Pre Preferred Bidder FBC production | Process | |
Pre Preferred Bidder FBC submission | Process | |
Phase 2 of PRG 2nd Stage Review (if selected) with the aim of accommodating within the overall 7 wks | (3) | |
Pre Preferred Bidder FBC production clarification | Process | |
Pre Preferred Bidder FBC approval | Process | |
Selection of Preferred Bidder | Event | |
Preferred Bidder (PB) Stage | (35) | 104 |
Authority appointment of Preferred Bidder | 4 | |
Alcatel Period and De-Briefing of Unsuccessful Bidder | 2 | |
Clarification and Fine-Tuning | 4 | |
Production of Planning Application | 6 | |
Submission of Planning Application | Event | |
Authority Planning Approval | 6 | |
Planning Judicial Review Period | 13 | |
Other Statutory Consents secured / PA position agreed | Process | |
Final clarification, fine-tuning and due diligence | Process | |
Pre-Financial Close Approval | 8 for below | 139 |
Pre-Financial Close Final Business Case (FBC) production | Process | |
Pre-Financial Close FBC submission | Event | |
Pre-Financial Close FBC clarification | Process | |
Pre-Financial Close Final FBC approval | Event | |
Authority Approval & Contract Award | Event | 147 |
Contract and Financial Close | 2 | 149 |
Mobilisation Period | 7 | 156 |
Services Commencement | 0 | 156 |