The Department based its calculations of Laser's entitlement on provisions relevant to terminating the contract for default on the part of Laser

4.2  When the parties drafted the contract, they had not contemplated a negotiated termination so no governing provisions existed. The gap had to be filled by creating a new agreement to effect the termination (Figure 12). The termination sum was therefore an outcome of bargaining between the Department, Laser and the Lenders.

12

The main elements of the termination agreement

Payment of the termination sum to Laser and transferring ownership of the assets to the Department. Consequently, the Department was no longer liable for paying the unitary charge of £11.5 million (1998 prices) per annum.

The Department's step-in to Laser's contract with its facilities management contractor, Serco Limited

The transfer of all warranties covering the assets from Laser to the Department

Entitlement for the Department to pursue claims against JLC Ltd in Laser's name

Source: National Audit Office

4.3  To inform its negotiating position, the Department used provisions in the contract governing a termination on the grounds of Laser's default, under which the Department had to pay a termination sum that was the lesser of:

  The Lenders' liabilities.

  Laser's budgeted construction costs7 in 1998, as amended by the cost of subsequent variations ordered by the Department; less 105 per cent of (a) the Department's costs of completing the outstanding work and (b) any unpaid liquidated damages owed by Laser to the Department.




__________________________________________________________________________________________

7  Under the contract, Laser's budgeted construction costs included construction costs, start up costs incurred by Laser's facilities management contractor, capital purchases, insurance, interest, and fees but excluded VAT.