Use of the public sector comparator

10.  To help in assessing whether or not to go ahead with a PFI option, departments are required to prepare a public sector comparator-an estimate of what a project would cost if conventional procurement methods were used. The Department prepared a Public Sector Comparator in 1997 and revised it in 1998 after ICL raised its bid. The net present value of ICL's bid was in each case cheaper than the Public Sector Comparator figure used (Figure 3).10

Figure 3: Comparison between ICL's bids and a Public Sector Comparator

 

ICL original bid 

£m

Public Sector Comparator

£m

ICL revised bid

£m

Revised
Public Sector Comparator

£m

Bid

146

174

184

178

Project/contract management

10

5

9

5

Total costs

156

179

193

183

Readily realisable benefit, risk and residual value

(130)

(149)

(137)

(139)

Net cost

26

30

56

44

Net Present Value

15.7

30.1

37.7

39.2

Source: Lord Chancellor's Department

11.  The Department acknowledged, however, that the Public Sector Comparator was not really comparable since it did not provide a national infrastructure linking Magistrates' Courts Committees together. At the time the Department felt that it had to go for the PFI route unless it could demonstrate conclusively that another approach could produce the solution required. The comparison between ICL's bids and a public sector comparator was a theoretical exercise because the Department had no IT department that could deliver a realistic alternative.11




_______________________________________________________________

10  C&AG's Report, para 2.19

11  Qq 22-23, 40, 118