The Procurement of the National Roads Telecommunications Services
SUMMARY
PART ONE The project is intended to enable the Agency's role as a road network operator
PART TWO The Agency secured a PPP that transferred risk at a cost that was slightly less than the estimated cost of a conventional procurement
PART THREE The cost of professional advice and the procurement timetable exceeded estimates
PART FOUR The new services are up and running and benefits are starting to flow
[APPENDICES]