PART TWO The Agency secured a PPP that transferred risk at a cost that was slightly less than the estimated cost of a conventional procurement

In September 2005, over five years after starting the procurement, the Agency and GeneSYS signed a Public Private Partnership contract for the NRTS. Despite delays in the tendering period, the Agency preserved competitive tension almost to the selection of a preferred bidder, avoided deal drift afterwards and secured contractual arrangements close to the terms it wanted.